County approves advertising for bids on new pool
News February 15, 2021
ELLIJAY, Ga. – Engineering reports are completed and in the hands of the Commissioners for their pool project.
The project saw a delay early this month when COVID hit the engineering firm causing a major quarantine. However, with the specs and the firm working alongside Project Leader Loy Jarrett and County Attorney David Clark, reports indicate that Gilmer could be bidding out the project as early as mid-March.
Commission Chairman Charlie Paris said that the advertisement will have to be open for four weeks as it is a public works project, which means bidding would last into May. Citizens could see the county awarding the bid in their May Regular Meeting.
One change to previous designs came with modifications to move the diving well to the right side, from the center. That is moved to the right hand side when viewed from the civic center.
One point of note that Post Commissioner Hubert Parker put forth was to inform citizens that the progress is underway and while the designs are in, the finalization of the bid package is being undertaken as a part of the same project with the firm.
With that, citizens could be seeing physical progress on construction in May or June after that bid process is completed, awarded, and the contracted company begins the project.
The county was looking to a special called meeting towards the end of February to look at final approval for advertising the project for bids and a few other items. However, with optimistic news coming on the day of the Regular Meeting, the Commissioners did move forward with approving advertisement of the bid package upon completion.
With that approval, the next step is to wait for the advertisement period and bid openings before citizens will know which company will be actually building the new pool.
Pool project hits another delay with COVID
News February 4, 2021
ELLIJAY, Ga. – Reports during a special called meeting of the Gilmer Board of Commissioners (BOC) indicate that the county’s pool project hit another delay this month.
Loy Jarret reported to the board that the engineering firm the county is using has been hit by the COVID virus. Due to this, at least a two week delay is coming to the pool construction project.
According to Jarrett, a large portion of the project is finished but the firm is now awaiting recovery and quarantine periods to end and for the firm to reconvene in order to finish the project. This means Gilmer will also see a delay in the promised 3 weeks originally promised. This could come closer to 6 weeks now.
The board is hoping to have the engineering finalized in February before returning to scheduling on the project which has been plagued with delays and issues including many from the ongoing Coronavirus outbreak and resurgence.
The pool project is attempting to continue under conditions after a major delay saw the Commissioners halt the project completely after demolition of the old pool last year. The commissioners, at that time, wanted to wait and see what the virus outbreak, quarantines, and self isolations would do to the county’s economy.
In the same area of the county, at River Park, the commissioners also approved an easement for Georgia Power to begin excavation and subsequent repairs to areas of the park to install underground utilities. According to County Attorney David Clark, the county will be making some minor changes to the agreement before returning it to Georgia Power for final approval.
With that, citizens could be seeing more immediate construction work in the area of River Park stretching through different areas. This construction work is not a part of the pool project, but rather Georgia Power performing this installation.