MARYVILLE, TN.- A lane closure on Church Ave. began on Oct. 10 in Maryville, TN. the project is projected to last until Jan. 2023.

Atmos Energy will begin a gas line replacement project downtown along Church Avenue on Oct. 10, 2022. The work will require the closure of the northeast-bound lane from Cates to Norwood.
The first phase of the work will start at Cates Street and work towards Cusick Street with plans to finish this section by Thanksgiving. The next phase will continue along Church Avenue from Cusick to Norwood.
This project is expected to be completed in Jan. 2023. Motorists should consider an alternate route. If an alternate route is not available, please slow down and use extra caution.
For more information, contact Engineering at (865) 273-3500. For more updates on the project check out https://www.maryvillegov.com/?fbclid=IwAR2ibq0ZXusmBtxlRHrgJuQG47jMQ5No5RTIUnX4PdbrEWQqcEixI7Fm8lc.
<