County approves advertising for bids on new pool
News February 15, 2021ELLIJAY, Ga. – Engineering reports are completed and in the hands of the Commissioners for their pool project.
The project saw a delay early this month when COVID hit the engineering firm causing a major quarantine. However, with the specs and the firm working alongside Project Leader Loy Jarrett and County Attorney David Clark, reports indicate that Gilmer could be bidding out the project as early as mid-March.
Commission Chairman Charlie Paris said that the advertisement will have to be open for four weeks as it is a public works project, which means bidding would last into May. Citizens could see the county awarding the bid in their May Regular Meeting.
One change to previous designs came with modifications to move the diving well to the right side, from the center. That is moved to the right hand side when viewed from the civic center.
One point of note that Post Commissioner Hubert Parker put forth was to inform citizens that the progress is underway and while the designs are in, the finalization of the bid package is being undertaken as a part of the same project with the firm.
With that, citizens could be seeing physical progress on construction in May or June after that bid process is completed, awarded, and the contracted company begins the project.
The county was looking to a special called meeting towards the end of February to look at final approval for advertising the project for bids and a few other items. However, with optimistic news coming on the day of the Regular Meeting, the Commissioners did move forward with approving advertisement of the bid package upon completion.
With that approval, the next step is to wait for the advertisement period and bid openings before citizens will know which company will be actually building the new pool.